tappan zee bridge

tappan zee soffit slabs

Each fully constructed Soffit Slab were the size of a football field and was lowered into the water all at once. Each piece that contributed to the constructed soffit weighed approx. 50-tons to 95-tons individually.

product

Soffit Slabs (QTY: 82)

tappan zee Pier caps

Originally designed as a cast-in-place product, CPS proposed a precast design. This saved TZC additional labor expenses and shortened the construction schedule by months.

Product

300-ton Pier Caps (QTY: 59) measuring up to 92’ Long x 10’-6” Wide x 13’-6” Tall

tappan zee cross beams

All four beams were cast on a barge, on budget, and delivered ahead of schedule.  Each beam weighed roughly 900-tons.

product

900-ton Cross Beams  (QTY: 4)

Details

Location: New York, New York

Owner: New York State Thruway Authority

Customer: TZ Constructors